Williams Mullen Law Office
Martin Horn was able to install $400,000 worth of high-end interior finishes for Williams Mullen in under 3 months. Javier Luevano led the effort to complete this space within budget in an extremely short time period without sacrificing the user’s demand for a quality project. With tenants in the spaces above and below, Martin Horn was able to complete this fitout without disturbing any existing occupants.
PROJECT START: July 2005
PROJECT SIZE: 4,500 SF
PROJECT DURATION: 3 months
CONTRACT VALUE: $422,568
CONTRACT TYPE: GMP w/shared savings
PROJECT MANAGER: Javier Luevano
SUPERINTENDENT: Everett Bradburn
ESTIMATOR: Dennis Harris
OWNER: Williams Mullen
CONTACT: Bruce Pritchard
ARCHITECT: Southern Air Design Build MEP
CONTACT: Daniel Crawley