UVA Scott Stadium
Jack M. Horn operated as the senior project manager on the press and president’s boxes, miscellaneous site work and drywall packages. Working with VMDO as the architect, Martin Horn was able to fully complete the stadium projects on time and within cost estimates.
PROJECT | DURATION |CONTRACT VALUE
Scoreboard | May ’98 – Mar ’99 | $948,466
Drywall | Nov ’98 – Mar ’01 | $2,771,501
Press/President’s Box | Feb ’99 – Sept ’00 | $2,871,871
Site Improvements | Feb ’99 – Sept ’00 | $1,712,806
Temporary Partitions | July ’99 – Dec ’99 | $107,931
Lower Seating | April ’99 – May ’99 | $112,045
PROJECT START: May 1998
PROJECT SIZE: 61,500 persons
CONTRACT VALUE: $8,524,620
CONTRACT TYPE: Lump Sum
PROJECT MANAGER: Jack M. Horn
SUPERINTENDENT: Jeff Sims
ESTIMATOR: Jack M. Horn
OWNER: University of Virginia
CONTACT: Richard Laurance
ARCHITECT: VMDO
CONTACT: Joe Celentano