UVA Hospital ER & Digestive Health Suites
John D. (Jack) Horn was the project manager and Mike McNulty the superintendent on this 13-phase, $6 million project. Jack and Mike’s abilities to work with the hospital staff and keep current on all changes was critical to the successful completion of this project. Despite numerous owner changes, Martin Horn was still able to meet the scheduled completion date and the ER was able to keep its mandated minimum number of open beds throughout the project.
PROJECT START: January 1999
PROJECT SIZE: 36,000 SF
PROJECT DURATION: 24 months
CONTRACT VALUE: $5,801,625
CONTRACT TYPE: Lump Sum
PROJECT MANAGER: John D. (Jack) Horn
SUPERINTENDENT: Mike McNulty
ESTIMATOR: Doug Horn
OWNER: University of Virginia
CONTACT: Fred Dunn
ARCHITECT: Ellerbe Becket, Inc.
CONTACT: Marie Brouder