Monticello Visitor Center
The Monticello Visitor Center, a 42,000 sf facility, has been designed to provide “enhanced” educational facilities, an exhibit building, a retail area, and a new ticket building all at the site of the existing ticket office and shuttle station. Martin Horn was a subcontractor to Barton Malow, as we contracted to do the exterior woodwork.
PROJECT START: June 2007
PROJECT DURATION: 15 months
CONTRACT VALUE: $2,015,840
CONTRACT TYPE: Lump Sum
PROJECT MANAGER: Javier Luevano & Chad Noble
SUPERINTENDENT: Mike Marks
ESTIMATOR: Doug Horn
OWNER: Thomas Jefferson Foundation
CONTACT: Mike Merriam
ARCHITECT: Ayers Saint Gross
CONTACT: Robert Claiborne