First United Methodist Church
The First United Methodist Church project included a small addition, some site work, and a major renovation that included significant mechanical, electrical, and plumbing components. Martin Horn also installed an elevator and an intricate millwork package. We faced challenging demolition while trying to incorporate modern infrastructure in an historic building, however, the church remained operational throughout.
PROJECT START: October 2001
PROJECT SIZE: 20,500 SF
PROJECT DURATION: 21 months
CONTRACT VALUE: $2,276,000
CONTRACT TYPE: CM At Risk
PROJECT MANAGER: Andy Sterling
SUPERINTENDENT: Everett Collins
ESTIMATOR: Doug Horn
OWNER: First United Methodist Church
CONTACT: Keith Rittenhouse
ARCHITECT: Sam Darnell